Harbor Lofts — Phase 2 · from Work

Tranche board

Release gates tied to the budget lines above
← Budget lines Hold all Release T3
Current budget
$14.78M
Deployed
$6.80M
Open ask (T3)
$2.40M
Lines in this ask
6
Over on those lines
+$90k + CO
Paid
01

Site & demo

$1.80M
1 budget line · closed
  • Paid$1.80M
  • Vs budget$0
  • Photos12
  • InspectionPassed
Paid
02

Structure

$4.40M
1 line · retainage open
  • Paid$4.40M
  • Owed$80k
  • Photos28
  • InspectionPassed
Open
03

Envelope & MEP

$2.40M
6 lines · 2 over budget
Locked
04

Interiors

$3.69M
Opens after T3 · +CO
  • Current budget$3.69M
  • Deployed$0
  • Draft SOVReady
  • Wire—
Locked
05

Close-out

$2.30M
Retainage 10%
  • Current budget$2.30M
  • Punch list—
  • CO—
  • Wire—
Open tranche pulls from Work lines — Windows already +$90k over; HVAC CO still pending Approve. See budget lines →