Harbor Lofts — Phase 2
Fund is Northbridge. Builder is Apex. You see committed, deployed, and still needed — same numbers the fund uses, without edit rights.
Tranche 3 in gate
−$180k under budget
T1–T2 released
Your commit
$2.0M
Called
$860k
Project deployed
$6.8M
Still needed
$8.1M
Budget vs deployed
Top lines (read-only)
LineCurrentPaidVs
Structure$4.48M$4.40M−$80k
Windows$830k$680k+$90k
HVAC$480k$0CO pend
Interiors$3.69M$0locked
Close-out$2.30M$0locked
Tranche timeline
Where money is in the gate
01
SiteReleased02
StructureReleased03
Envelope$2.4M ask04
InteriorsLocked05
CloseLockedTwo open lines are over plan. Fund decides release; you only watch the capital picture update.